Karachi’s long-delayed K-IV bulk water supply project is now expected to be completed by June 2027, extending its timeline once again as lawmakers seek accountability for repeated delays.
WAPDA officials shared the revised completion target during a meeting of a National Assembly sub-committee on Water Resources, where members reviewed the project’s progress, design complications and planning issues. Lawmakers expressed concern over the prolonged delays, stressing that the scheme is essential to meeting Karachi’s growing water demand and should face no further setbacks.
The project was conceived by the Sindh government in 2003 to address the city’s drinking water shortage. Civil works began in July 2016, with an initial completion deadline of December 2018. However, design-related problems delayed progress, and a third-party investigation commissioned by the Sindh government later identified shortcomings in the original design.
The federal government took over the project under the Karachi Transformation Plan in 2020. WAPDA assumed responsibility in April 2021 and began mobilisation in September 2022. Although the scheme was initially scheduled for completion by October 2023, the deadline has now been revised to June 2027. Officials said the revised design and planning have been submitted to the Planning Commission and federal government.
The K-IV project is designed to bring 650 million gallons per day (MGD) of water from Keenjhar Lake in Thatta to Karachi in three phases. Phase-I will provide 260 MGD through supply points at Pipri, North East Karachi and Manghopir. The remaining phases are planned to add another 390 MGD.
The first phase includes an intake structure at Keenjhar Lake, a gravity channel, pumping facilities, a pressurised pipeline, reservoirs and filtration plants. The Sindh government is responsible for the distribution network, power arrangements, land acquisition and right-of-way clearance.
WAPDA officials told the committee that Karachi’s water requirement stands at around 1,200 MGD, highlighting the importance of the project in addressing the city’s supply shortfall. Once completed, the Karachi Water and Sewerage Corporation will take over its operation and maintenance.