Pakistan has once again postponed approval of its $1 billion Main Line-3 (ML-3) railway rehabilitation project, marking the third delay in five months. The Central Development Working Party (CDWP) deferred the Rs278 billion project amid financing concerns and uncertainty over the proposed route for transporting minerals from the Reko Diq mining project.
The project involves rehabilitating around 996 kilometres of railway track between Nokhandi and Rohri. The existing infrastructure has exceeded its operational life, with trains travelling at an average speed of around 30 kilometres per hour. The upgrade includes track renewal, bridge and embankment rehabilitation, replacement of turnouts and construction of 11 new railway stations.
A major concern is a proposed $390 million bridge loan from Reko Diq Mining Company, carrying an estimated annual interest rate of 6%. Pakistan is expected to repay the loan in a single payment by June 2028, with the total repayment potentially reaching nearly $450 million. However, officials are reviewing whether the financing arrangement would remain valid if mineral exports shift from Karachi Port to Gwadar.
The government is also considering the Nokhandi-Panjgur-Gwadar route to facilitate mineral transportation. Planning Minister Ahsan Iqbal has called for coordination among relevant government departments and mining companies to address financing and technical issues. Meanwhile, the Planning Commission has warned that inadequate funding could cause further delays and increase project costs. Only Rs250 million has been allocated to ML-3 in the current fiscal year.