Two underpasses at Race Course Park and Charing Cross in Rawalpindi have reached 75% completion, with both projects expected to be completed by the end of December 2026. The Punjab Highway Department is constructing the underpasses as part of a planned signal-free corridor connecting Koral Chowk with Motorway Chowk.
The Race Course Park underpass will have two lanes for northbound traffic, while the Charing Cross underpass will facilitate southbound traffic through two lanes. The projects also include multi-level road arrangements to improve vehicle movement and reduce traffic congestion. Meanwhile, authorities are rehabilitating and expanding the road along Peshawar Road and shifting utility services underground.
Both underpasses are part of a wider 25-kilometer signal-free corridor that also includes the completed remodelling of Kutchery Chowk and construction of the GPO underpass. The Punjab government aims to complete the entire corridor by June 2027, reducing travel time between Islamabad Expressway and Motorway Chowk to approximately 15 to 20 minutes.